How does an Ivalua implementation work?

The short answer

An Ivalua implementation sets up the standard platform for your processes, connects your ERP, loads your data and goes live. A certified integrator and your own key users do the work. One scope takes months.

What is an Ivalua implementation?

An Ivalua implementation is the project that turns the standard Ivalua platform into your organisation’s procurement system. Your processes and approval workflows are set up. Your supplier and contract data is loaded. Your ERP is connected. Ivalua is configured rather than coded, so most of the work is design and configuration, plus interfaces and data.

The scope can be one area, such as procure-to-pay or source-to-contract, or the full source-to-pay suite. eProcurement Toolkit has neutral guides to what these processes cover: procure-to-pay and procurement software. This page is about doing it on Ivalua.

What are the phases of an Ivalua project?

Integrators give their phases different names, but every Ivalua project follows the same order. The order matters more than the names. Each phase needs decisions that were taken in the phase before.

  1. Framing: the scope (modules, entities, countries), governance, and the team on both sides. You also decide which system owns each type of data (suppliers, cost centres, items). For example: is a new supplier created in Ivalua or in the ERP?
  2. Design: your processes are mapped onto the standard. Each change to the standard is decided and written down. Ivalua’s 2023 terms provide for Ivalua to review the customer’s design document.
  3. Build: Level 2 certified people configure the platform. Level 3 certified people build the interfaces with the ERP and other systems.
  4. Data: supplier, contract and catalogue data is cleaned, mapped and loaded, with checks for duplicates and quality.
  5. Testing: interfaces are tested end to end. Then your key users run the user acceptance tests, with written go/no-go criteria.
  6. Training and go-live: users are trained. You switch from the old system to the new one (cutover). Then a team gives close support (hypercare) while the first transactions run.
  7. Run and upgrades: support, changes, and an upgrade at least every two years under Ivalua’s terms.

A large programme repeats the steps from build to go-live for each lot or entity. For example, Groupe BPCE redeployed its Ivalua platform in three lots on the standard. Before each lot, it ran a gap analysis: a list of what the standard does not cover. On the BNP Paribas v182 programme I work on, the new solution runs in parallel with the old one. Entities and users switch over step by step. The v182 case study describes it.

Who does what on an Ivalua implementation?

PartyWhat they bringWhat the public sources say
Your procurement teamProcess owners and key users who take the design decisions and run the acceptance testsHDF Energy went live in 3 months; the case names the client team’s availability in design and testing as a condition
Your IT teamERP interfaces, user access and single sign-on, data extraction, environmentsMaryland contracted a 22-week job to extract data from its Ivalua platform into its financial system
A certified integrator or consultantsConfiguration, integrations, project methodIvalua’s 2023 terms require Level 2 certification to configure and Level 3 for integrations
IvaluaThe platform, support, upgrades, customer successThe terms provide a design review by Ivalua and a business review every quarter with a customer success manager
Sponsor and steering committeeScope decisions, and decisions when teams disagreeForrester’s model company (study commissioned by Ivalua) had 8 internal full-time staff during implementation
Roles on an Ivalua implementation, with what Ivalua’s published terms and public cases say about each

The integrator configures. But the scope, the design decisions, the data and the acceptance tests stay with you.

You can implement with one of Ivalua’s integration partners, with independent certified consultants, or with a mix of both next to your own team. How to choose is covered in Ivalua implementation partner. If you need certified Ivalua people, I take senior missions or lead a team from my network.

What makes an Ivalua implementation go wrong?

Public cases show the same few causes. None of them comes from the software. Each one is easier to see early than to fix late.

  • Changes to the standard. Ivalua’s terms charge complex configuration and integrations added after go-live at every upgrade. For example, an approval rule built only for your company must be checked and tested again at each upgrade. BPCE rebuilt its Ivalua platforms on the standard. BNP Paribas rebuilt its platform from scratch on v164 because v156 had many complex specific configurations (v164 case study).
  • Key users who are not available. The fast cases (HDF Energy in three months) name the client team’s availability in design and testing as a condition.
  • Data that arrives late. Supplier data must be clean before testing means anything. You must also have decided which system owns each type of data.
  • Interfaces tested late. If ERP flows are tested end to end only during acceptance testing, every defect becomes a delay. Ivalua ERP integration lists the flows to test.
  • A project that nobody stops. Maryland’s Ivalua project was signed in March 2019. In December 2023 it was still only partly completed. The State then ordered a six-week assessment and planned a new contract to finish it.

How much does it cost and how long does it take?

Public cases range from 8 weeks for a packaged procure-to-pay scope to six to ten months for a multi-module suite. In Forrester’s model, commissioned by Ivalua, licence fees were only about a quarter of the three-year cost. The figures, the contracts behind them and the cost items are in Ivalua implementation cost and timeline.

Which other questions do the next guides answer?

This page gives an overview of the implementation. Each specific question has, or will have, its own guide:

Frequently asked questions

Short answers to the questions people ask, each one sourced above.

Can we implement Ivalua without an integrator?

Not with untrained staff. Ivalua’s 2023 terms require Level 2 certification to configure the platform and Level 3 for integrations, or a certified partner. The certified people can be an integrator, independent certified consultants, or your own staff once they are certified.

Is an Ivalua implementation configuration or development?

Mostly configuration. Ivalua describes a no-code configuration toolkit and Design Mode on one codebase. Interfaces, data loads and reports add technical work, often SQL. The risk is not code. It is the changes to the standard, which Ivalua’s terms charge again at each upgrade.

What happens after go-live?

First a period of close support (hypercare), then the run: support, changes and upgrades. Ivalua’s 2023 terms recommend an upgrade every 12 to 18 months and require one at least every two years. Public buyers often sign a separate contract for the run, for three to eight years.

Have you implemented Ivalua yourself?

Yes. I have worked hands-on on three full-cycle Ivalua implementations for BNP Paribas: v156, v164 and v182. I worked on design, configuration, integrations, custom SQL, migration and change management on entity rollouts. The figures of those programmes belong to the client.

Project already started? Check where it stands.

The health check scores your platform and your programme in three weeks.

See the health check
Seb Troz

Seb Troz

Certified Ivalua consultant (L1–L3). Three full-cycle implementations at BNP Paribas (v156, v164, v182), programme manager at Vallourec. Led a team of 13 on Rapsody at Société Générale. Engineer, ENSIMAG. About Seb