Key takeaways
- An Ivalua implementation is configuration of a standard platform, not software development: the decisions that cost most later are the departures from that standard.
- Ivalua’s published terms require certified people: Level 2 to configure, Level 3 to build integrations, and a design review by Ivalua.
- Your own team carries a large share of the work: Forrester’s Ivalua-commissioned composite counted 8 internal full-time staff during implementation.
- Go-live is not the end: Ivalua requires an upgrade at least every two years, and complex configuration added after go-live is charged again at each one.
What is an Ivalua implementation?
An Ivalua implementation is the project that turns the standard Ivalua platform into your organisation’s procurement system: your processes configured, your approval workflows set up, your supplier and contract data loaded, your ERP connected. Ivalua is configured rather than coded, so most of the work is design and configuration, plus interfaces and data.
The scope can be one area, such as procure-to-pay or source-to-contract, or the full source-to-pay suite. For the general picture of what those processes cover, eProcurement Toolkit has neutral guides to procure-to-pay and procurement software. This page is about doing it on Ivalua.
What are the phases of an Ivalua project?
Integrators name their phases differently, but an Ivalua project moves through the same sequence. The order matters more than the names: each phase depends on decisions the previous one closed.
- Framing: scope (modules, entities, countries), governance, the team on both sides, and which system is master for each object (suppliers, cost centres, items).
- Design: processes mapped onto the standard, each departure from it decided and written down; Ivalua’s 2023 terms provide for Ivalua to review the customer’s design document.
- Build: configuration in the platform by Level 2 certified people, interfaces with the ERP and other systems by Level 3 certified people.
- Data: supplier, contract and catalogue data cleaned, mapped and loaded, with controls on duplicates and quality.
- Testing: interfaces tested end to end, then user acceptance testing by your key users, with written go/no-go criteria.
- Training and go-live: users trained, cutover, then hypercare while the first transactions run.
- Run and upgrades: support, changes, and an upgrade at least every two years under Ivalua’s terms.
A large programme repeats the build-to-go-live loop by lot or by entity. Groupe BPCE, for example, redeployed its Ivalua platform in three lots on the standard, with a gap analysis before each lot. On the BNP Paribas v182 programme I work on, the new solution runs in parallel with the old one while entities and users switch over progressively; the v182 case study describes it.
Who does what on an Ivalua implementation?
| Party | What they bring | What the public sources say |
|---|---|---|
| Your procurement team | Process owners and key users who decide the design and run the acceptance tests | HDF Energy’s 3-month go-live names the client team’s availability in design and testing as a condition |
| Your IT team | ERP interfaces, identity, data extraction, environments | Maryland contracted a 22-week job to extract data from its Ivalua platform into its financial system |
| A certified integrator or consultants | Configuration, integrations, project method | Ivalua’s 2023 terms require Level 2 certification to configure and Level 3 for integrations |
| Ivalua | The platform, support, upgrades, customer success | The terms provide a design review by Ivalua and quarterly business reviews with a customer success manager |
| Sponsor and steering committee | Scope decisions and arbitration | Forrester’s composite counted 8 internal full-time staff during implementation |
The integrator configures, but the scope, the design decisions, the data and the acceptance tests stay with you.
You can implement with one of Ivalua’s integration partners, with independent certified consultants, or with a mix next to your own team. Choosing between them is the subject of a planned guide on the Ivalua implementation partner. If you need certified Ivalua capacity, I take senior missions or lead a team from my network.
What makes an Ivalua implementation go wrong?
Public cases point to the same few causes. None of them is specific to the software; each one is easier to see early than to fix late.
- Departures from the standard. Ivalua’s terms charge complex configuration and integrations added after go-live at every upgrade. BPCE rebuilt its Ivalua platforms on the standard; BNP Paribas rebuilt its platform from scratch on v164 because v156 carried many complex specific configurations (v164 case study).
- Key users who are not there. The fast cases (HDF Energy in three months) name the availability of the client team in design and testing as a condition.
- Data that arrives late. Supplier data has to be clean, and the master system for each object decided, before testing can mean anything.
- Interfaces tested late. ERP flows tested end to end only during acceptance testing turn every defect into a delay.
- A project that nobody stops. Maryland’s Ivalua project, signed in March 2019, was still only partially completed in December 2023, when the State ordered a six-week assessment and planned a new contract to finish it.
How much does it cost and how long does it take?
Public cases range from 8 weeks for a packaged procure-to-pay scope to six to ten months for a multi-module suite, and licence fees were only about a quarter of the three-year cost in Forrester’s Ivalua-commissioned composite. The figures, the contracts behind them and the cost components are in Ivalua implementation cost and timeline.
Which questions does this cluster answer next?
This page sums up the implementation. Each specific question has, or will have, its own guide:
- Cost and timeline: Ivalua implementation cost and timeline.
- Choosing an integrator or independent consultants: Ivalua implementation partner (planned).
- Connecting Ivalua to SAP, Oracle or another ERP: Ivalua ERP integration (planned).
- Moving from SAP Ariba: SAP Ariba to Ivalua migration (planned).
- Levels L1 to L3 and who needs them: Ivalua certification (planned).
Frequently asked questions
Short answers to the questions people ask, each one sourced above.
Can we implement Ivalua without an integrator?
Not with untrained staff. Ivalua’s 2023 terms require Level 2 certification to configure the platform and Level 3 for integrations, or a certified partner. The certified people can be an integrator, independent certified consultants, or your own staff once certified.
Is an Ivalua implementation configuration or development?
Mostly configuration: Ivalua describes a no-code configuration toolkit and Design Mode on one codebase. Interfaces, data loads and reports add technical work, often SQL. The risk is not code but departures from the standard, which Ivalua’s terms charge again at each upgrade.
What happens after go-live?
Hypercare first, then run: support, changes and upgrades. Ivalua’s 2023 terms recommend an upgrade every 12 to 18 months and require one at least every two years. Public buyers often contract the run separately, for three to eight years.
Have you implemented Ivalua yourself?
Yes. I have worked hands-on on three full-cycle Ivalua implementations for BNP Paribas, v156, v164 and v182: design, configuration, integrations, custom SQL, migration and change management on entity rollouts. The figures of those programmes belong to the client.
Already running? Check where you stand.
The health check scores your platform and your programme in three weeks.