For the third full Ivalua cycle at BNP Paribas, a new solution was built from scratch to move the platform from v164 to v182. It was delivered on schedule, performs better and is still evolving. The old and new versions run side by side while entities and users move over.

Client
BNP Paribas
Platform
Ivalua v182
Role
Techno-functional consultant, S2P/ERP
Period
July 2025 – now
Status
Delivered, still evolving; old and new versions in parallel during the switch-over

Three versions, one client

I built and deployed the group S2P platform on v156, then redesigned it completely on v164. Then I delivered a new v182 solution, built from scratch and still evolving: ERP and supplier interfaces, migration, advanced SQL.

  1. v156

    Build and deploy

    Suppliers, sourcing, CLM, catalogue, BPM, e-procurement

  2. v164

    Complete redesign

    Same group, everything designed again

  3. v182

    New solution, delivered and evolving

    Built new, ERP and supplier interfaces, migration

    Current

What was the v182 programme?

BNP Paribas runs its group source-to-pay on Ivalua. The platform was built on v156 and then redesigned completely on v164. The v182 programme is the third full cycle. It is a new solution built from scratch, not an upgrade of the existing v164 platform. I joined in July 2025 as a techno-functional Ivalua consultant. I work on the S2P side and on the interfaces with the ERP.

What is the status of the programme?

As of October 2026, v182 is delivered. It went live on schedule and is still evolving. The old and new versions now run in parallel. All entities and users move to v182 step by step, not all on the same day.

  1. Build the new v182 solution from scratch, with its interfaces.
  2. Migrate the data from v164, with quality controls and duplicate detection, up to sign-off.
  3. Go live on schedule.
  4. Run v164 and v182 in parallel.
  5. Move entities and users to v182 step by step, in France and internationally.

What did I do on v182?

WorkstreamMy hands-on scope
Design and configurationFunctional design of the new solution and its configuration in Ivalua
IntegrationsSupplier and ERP interfaces, catalogue, data flows between systems
Custom SQLAdvanced queries for reports, controls and data flows
MigrationThe full migration work: data quality controls, duplicate detection, documentation of each flow, up to sign-off
Change managementEntity rollouts in France and internationally
My scope on the BNP Paribas Ivalua v182 programme, from July 2025

One role covering functional and technical work: the design, the interfaces, the SQL and the data migration.

In the migration, each data flow is documented. Its data is checked for quality and for duplicates before sign-off. A duplicate is, for example, the same supplier created twice with two different spellings.

What was the outcome?

  • Delivered and still evolving: the new v182 solution is in production and continues to change.
  • On schedule: the go-live date was met.
  • Better performance than the version it replaces.
  • Switch-over in progress: entities and users move from v164 to v182 step by step. Both versions run in parallel until the switch-over ends.

No figures on entities, users, suppliers, team size or spend are published here: they belong to the client.

Which systems does v182 connect?

Ivalua v182 sits between the group ERP and the suppliers. I worked on the supplier interfaces, the ERP interfaces and the catalogue, and on the data flows between these systems. Custom SQL is used for the reports and for the controls that check those flows.

The three cycles are listed together on the case studies page.

Project already started? Check where it stands.

The health check scores your platform and your programme in three weeks.

See the health check